Sec. 11.62 Closed Circuit Tests of National Level EAS facilities.
(a) Closed Circuit Tests (CCT) of National Level EAS facilities
shall be conducted on a random or scheduled basis not more than once a
month and not less than once every three months. Test times will be
selected by the White House in coordination with participating industry
personnel, the Federal Emergency Management Agency (FEMA), and the FCC.
The FCC will notify the participating networks, wire services, cable
networks and program suppliers and common carriers of the selected time
window for the test at least four working days (holidays excluded)
before the test.
(b) The EAS Operating Handbook and National Control Point Procedures
contain the CCT procedures.
(c) The control points of the participating radio and television
networks, cable networks and program suppliers, wire services and common
carriers will receive notification of a CCT by a ``Closed Circuit Test
Activation Message''.
(d) Test announcements will originate from a point selected by the
White House with program feed circuitry connected to the telephone
company Toll Test Center at points coordinated for each test.
Participating common carriers will connect, as required, the facilities
of the radio networks and other test participants. Telephone companies
are not authorized to add any participating independent broadcast
stations unless authorized by the FCC. Authentication will be provided
to the Toll Test Center or other program entry location responsible for
test arrangements. Authentication used in the CCT Message will be the
test words on the outside of the Red Envelope Authenticator List.
(e) CCT procedures for radio network affiliates, wire service
subscribers, and, if participating, television network affiliates and
cable systems are as follows:
(1) Notification of a CCT will be disseminated as specified in
Sec. 11.53 (a)(1) and (a)(3) and the EAS Operating Handbook.
(2) Recipients immediately monitor their radio network, and if
participating, their television network or cable system, and check their
wire service for the receipt of the CCT Activation Message. Verify
authenticity using the current Red Authenticator List.
(3) Continue to monitor for the CCT audio talkup and program.
(4) Enter the time of receipt of the CCT message in the broadcast
station log or cable system records.
(5) The CCT terminates on the following aural closing cue in the
text of the test program: ``This concludes the Closed Circuit Test of
the EAS.''
(6) Following the closing cue, wire service subscribers will receive
a ``Closed Circuit Test Termination Message''. Record the time of
receipt as indicated above.
(f) The FCC may request a CCT report in a prescribed format.
Goto Section: 11.61 | 11.62
Goto Year: 1996 |
1998
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public