Sec. 32.2441 Conduit systems.
(a) This account shall include the original cost of conduit, whether
underground, in tunnels or on bridges, which is reusable in place. It
shall also include the cost of opening trenches and of any repaving
necessary in the construction of conduit plant.
[[Page 441]]
(b) The cost of pumping water out of manholes and of cleaning
manholes and ducts in connection with construction work and the cost of
permits and privileges for the construction of cable and wire facilities
shall be included in the account chargeable with such construction.
(c) The cost of protective covering for buried cable shall be
charged to Account 2423, Buried Cable, as appropriate, unless such
protective covering is reusable in place. The amounts thus charged shall
be included in the nonmetallic buried cable or metallic buried cable
subsidiary record category, as appropriate.
(d) The cost of pipes or other protective covering for underground
drop and block wires shall be included in Account 2421, Aerial Cable, or
Account 2423, Buried Cable, as appropriate. The amounts thus charged
shall be included in the nonmetallic or metallic subsidiary record
category, as appropriate.
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.