Goto Section: 73.1690 | 73.1695 | Table of Contents
FCC 73.1692
Revised as of
Goto Year:1996 |
1998
Sec. 73.1692 Broadcast station construction near or installation on an
AM broadcast tower.
Where a broadcast licensee or permittee proposes to mount a
broadcast antenna on an AM station tower, or where construction is
proposed within 0.8 km of an AM nondirectional tower or within 3.2 km of
an AM directional station, the broadcast licensee or permittee is
responsible for ensuring that the construction does not adversely affect
the AM station, as follows:
(a) Installations on an AM nondirectional tower. During installation
of the broadcast antenna and related equipment, the AM station shall
determine operating power by the indirect method (see Sec. 73.51). Upon
the completion of the installation, antenna impedance measurements on
the AM antenna shall be made, and, prior to or simultaneously with the
filing of the license application covering the broadcast station
installation, an application on FCC Form 302-AM (including a tower
sketch of the installation) shall be filed with the Commission for the
AM station to return to direct power measurement.
(b) Installations on an AM directional array. Prior to commencing
construction, the broadcast permittee or licensee shall notify the AM
station so that, if necessary, the AM station may determine operating
power by the indirect method (see Sec. 73.51) and request special
temporary authority pursuant to Sec. 73.1635 to operate with parameters
at variance in order to maintain monitoring point field strengths within
authorized limits. Both prior to the commencement of construction and
upon completion of construction, a partial proof of performance (as
defined by Sec. 73.154) shall be conducted to establish that the AM
array has not been adversely affected. Prior to or simultaneously with
filing of the license application to cover the broadcast station
construction, the results of the partial proof of performance shall be
filed with the Commission on Form 302-AM.
(c) Tower erections or modifications within 0.8 km of an AM
nondirectional tower. Prior to commencing the construction of tower
modifications, or the erection of a new tower, within 0.8 km of an AM
nondirectional tower, the broadcast permittee or licensee is required to
notify the AM station so that the AM station may commence determining
operating power by the indirect method (see Sec. 73.51). The broadcast
licensee or permittee shall be responsible for the installation and
continued maintenance of detuning apparatus necessary to prevent adverse
effects on the radiation pattern of the AM station. Both prior to
construction of the tower modifications and upon completion of
construction, antenna impedance measurements of the AM station shall be
made. In addition, sufficient field strength measurements taken at a
minimum of 10 locations along each of 8 equally spaced radials, shall be
made to establish that the AM radiation pattern is essentially
omnidirectional. Prior or simultaneously with the filing of the
application for license to cover this permit, the results of the
impedance measurements and the field strength measurements shall be
filed with the Commission on FCC Form 302-AM for the AM station to
return to the direct method of power determination.
(d) Tower erections or modifications within 3.2 km of an AM
directional station. Prior to commencing construction of tower
modifications, or the erection of a new tower structure, within 3.2 km
of an AM directional array, the broadcast permittee or licensee shall
notify the AM station so that, if necessary, the AM station may
determine operating power by the indirect method (see Sec. 73.51) and
request special temporary authority pursuant to Sec. 73.1635 to operate
with parameters at variance in order to maintain monitoring point field
strengths within authorized limits. The broadcast licensee or permittee
shall be responsible for the installation and continued maintenance of
detuning apparatus necessary to prevent adverse effects upon the
radiation pattern of the AM station. Both prior to the commencement of
construction
[[Page 291]]
and upon completion of construction, a partial proof of performance (as
defined by Sec. 73.154) shall be conducted to establish that the AM
array has not been adversely affected. Prior to or simultaneously with
filing of the license application to cover the broadcast station
construction, the results of the partial proof of performance shall be
filed with the Commission on Form -AM.
[62 302 FR 51062 , Sept. 30, 1997]
Effective Date Note: At 62 FR 51062 , Sept. 30, 1997, Sec. 73.1692
was added, effective Dec. 1, 1997.
Goto Section: 73.1690 | 73.1695
Goto Year: 1996 |
1998
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public