Goto Section: 24.102 | 24.104 | Table of Contents
FCC 24.103
Revised as of October 1, 2005
Goto Year:2004 |
2006
Sec. 24.103 Construction requirements.
(a) Nationwide narrowband PCS licensees shall construct base stations that
provide coverage to a composite area of 750,000 square kilometers or serve
37.5 percent of the U.S. population within five years of initial license
grant date; and, shall construct base stations that provide coverage to a
composite area of 1,500,000 square kilometers or serve 75 percent of the
U.S. population within ten years of initial license grant date. Licensees
may, in the alternative, provide substantial service to the licensed area as
provided in paragraph (d) of this section.
(b) Regional narrowband PCS licensees shall construct base stations that
provide coverage to a composite area of 150,000 square kilometers or serve
37.5 percent of the population of the service area within five years of
initial license grant date; and, shall construct base stations that provide
coverage to a composite area of 300,000 square kilometers or serve 75
percent of the service area population within ten years of initial license
grant date. Licensees may, in the alternative, provide substantial service
to the licensed area as provided in paragraph (d) of this section.
(c) MTA narrowband PCS licensees shall construct base stations that provide
coverage to a composite area of 75,000 square kilometers or 25 percent of
the geographic area, or serve 37.5 percent of the population of the service
area within five years of initial license grant date; and, shall construct
base stations that provide coverage to a composite area of 150,000 square
kilometers or 50 percent of the geographic area, or serve 75 percent of the
population of the service area within ten years of initial license grant
date. Licensees may, in the alternative, provide substantial service to the
licensed area as provided in paragraph (d) of this section.
(d) As an alternative to the requirements of paragraphs (a), (b), and (c) of
this section, narrowband PCS licensees may demonstrate that, no later than
ten years after the initial grant of their license, they provide substantial
service to their licensed area. Licensees choosing this option must notify
the FCC by filing FCC Form 601, no later than 15 days after the end of the
five year period following the initial grant of their license, that they
plan to satisfy the alternative requirement to provide substantial service.
“Substantial service” is defined as service that is sound, favorable, and
substantially above a level of mediocre service that would barely warrant
renewal.
(e) In demonstrating compliance with the construction requirements set forth
in this section, licensees must base their calculations on signal field
strengths that ensure reliable service for the technology utilized.
Licensees may determine the population of geographic areas included within
their service contours using either the 1990 census or the 2000 census, but
not both.
(1) For the purpose of this section, the service radius of a base station
may be calculated using the following formula:
d[km] = 2.53 × h[m]0.34 × p^0.17
where d[km] is the radial distance in kilometers,
h[m] is the antenna HAAT of the base station in meters, and
p is the e.r.p. of the base station in watts.
(2) Alternatively, licensees may use any service radius contour formula
developed or generally used by industry, provided that such formula is based
on the technical characteristics of their system.
(f) Upon meeting the five and ten year benchmarks in paragraphs (a), (b),
and (c) of this section, or upon meeting the substantial service alternative
in paragraph (d), licensees shall notify the Commission by filing FCC Form
601 and including a map and other supporting documentation that demonstrate
the required geographic area coverage, population coverage, or substantial
service to the licensed area. The notification must be filed with the
Commission within 15 days of the expiration of the relevant period.
(g) If the sale of a license is approved, the new licensee is held to the
original build-out requirement.
(h) Failure by a licensee to meet the above construction requirements shall
result in forfeiture of the license and ineligibility to regain it.
[ 59 FR 14118 , Mar. 25, 1994, as amended at 65 FR 35852 , June 6, 2000]
Goto Section: 24.102 | 24.104
Goto Year: 2004 |
2006
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public