Sec. 24.843 Extension of time to complete construction.
(a) If construction is not completed within the time period set forth in
Sec. 24.203, the authorization will automatically expire. Before the period for
construction expires an application for an extension of time to complete
construction (FCC Form 489) may be filed. See paragraph (b) of this section.
Within 30 days after the authorization expires an application for
reinstatement may be filed on FCC Form 489.
(b) Extension of Time to Complete Construction. An application for extension
of time to complete construction may be made on FCC Form 489. Extension of
time requests must be filed prior to the expiration of the construction
period. Extensions will be granted only if the licensee shows that the
failure to complete construction is due to causes beyond its control.
(c) An application for modification of an authorization (under construction)
does not extend the initial construction period. If additional time to
construct is required, an FCC Form 489 must be submitted.
(d) [Reserved]
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.