Goto Section: 90.627 | 90.631 | Table of Contents
FCC 90.629
Revised as of October 1, 2005
Goto Year:2004 |
2006
Sec. 90.629 Extended implementation period.
Applicants requesting frequencies for either trunked or conventional
operations may be authorized a period of up to five (5) years for
constructing and placing a system in operation in accordance with the
following:
(a) The applicant must justify an extended implementation period. The
justification must describe the proposed system, state the amount of time
necessary to construct and place the system in operation, identify the
number of base stations to be constructed and placed in operation during
each year of the extended construction period, and show that:
(1) The proposed system will require longer than twelve (12) months to
construct and place in operation because of its purpose, size, or
complexity; or
(2) The proposed system is to be part of a coordinated or integrated
wide-area system which will require more than twelve (12) months to plan,
approve, fund, purchase, construct, and place in operation; or
(3) The applicant is required by law to follow a multi-year cycle for
planning, approval, funding, and purchasing the proposed system.
(b) Where an applicant is required by law to follow a multi-year cycle for
planning, approval, funding and purchasing a proposed system, the applicant
must indicate whether funding approval has been obtained and if not, when
such funding approval is expected.
(c) Authorizations under this section are conditioned upon the licensee
constructing and placing its system in operation within the authorized
implementation period and in accordance with an approved implementation plan
of up to five years. Licensees must notify the Commission annually, using
FCC Form 601, that they are in compliance with their yearly station
construction commitments, but may request amendment to these commitments at
the time they file their annual certification. If the Commission approves
the requested amendments to a licensee's implementation commitments, the
licensee's extended implementation authority will remain in effect. If,
however, the Commission concludes, at this or any other time, that a
licensee has failed to meet its commitments, the Commission will terminate
authority for the extended implementation period. When the Commission
terminates an extended implementation authority, the affected licensee will
be given six months from the date of termination to complete system
construction. At the end of any licensee's extended implementation period,
authorizations for all stations not constructed and placed in operation will
be cancelled. Trunked systems granted an extended implementation period must
comply with the channel loading requirements of section 90.631(b).
Conventional channels not loaded to 70 mobile units may be subject to shared
use by the addition of other licensees.
(d) [Reserved]
(e) As of March 18, 1996, Specialized Mobile Radio systems are not eligible
for extended implementation periods under this section. Additionally, all
800 MHz SMR licensees that are operating under extended implementation
authority as of March 18, 1996 must, by May 16, 1996, demonstrate that
continuing to allow them to have an extended period of time to construct
their facilities is warranted and furthers the public interest. If a
licensee's extended implementation authority showing is approved by the
Bureau, such licensee will be afforded an extended implementation of two
years or the remainder of its current extended implementation period,
whichever is shorter. Upon the termination of this period, the
authorizations for those facilities that remain unconstructed will terminate
automatically. If a licensee with a current extended implementation period
fails to submit the showing mentioned above within the designated timeframe
or submits an insufficient or incomplete showing, such licensee will have
six months from the last day on which it could timely file such a showing or
from the disapproval of its request to construct the remaining facilities
covered under its implementation plan to construct any unconstructed
facilities for which it is authorized. The authorizations for those
facilities remaining unconstructed after this six-month period will
terminate automatically.
(f) Pursuant to Sec. 90.155(b), the provisions of this section shall apply to
local government entities applying for any frequency in the Public Safety
Pool.
[ 58 FR 34379 , June 25, 1993, as amended at 61 FR 6157 , Feb. 16, 1996; 63 FR 68969 , Dec. 14, 1998; 65 FR 60877 , Oct. 13, 2000; 69 FR 67489 , Nov. 22,
2004]
Goto Section: 90.627 | 90.631
Goto Year: 2004 |
2006
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public