FCC 27.1236 Revised as of October 1, 2006
Goto Year:2005 |
2007
Sec. 27.1236 Self-transitions.
(a) If an Initiation Plan is not filed within 30 months of July 19, 2006 for
a BTA, BRS and EBS licensees in that BTA may self-transition by relocating
to their default channel locations specified in Sec. 27.5(i)(2) and complying
with Sec. Sec. 27.50(h), 27.53, 27.55 and 27.1221.
(b) To self-transition, a BRS or EBS licensee must:
(1) Notify the Secretary of the Commission on or before 90 days after the
Initiation Plan must be filed with the Commission that it will
self-transition (see paragraph (a) of this section);
(2) Send a Self-Transition Notification (see paragraph (c) of this section)
to other BRS and EBS licensees in the BTA where the self-transitioning
licensee's GSA geographic center point is located that it is
self-transitioning;
(3) Notify other licensees whose GSAs overlap with the self-transitioning
licensee that it is self-transitioning.
(4) Address interference concerns with other BRS and EBS licensees in the
BTA that are also self-transitioning;
(5) File a modification application with the Commission, and
(6) Complete the self-transition within 57 months of July 19, 2006.
(c) Self-Transition Notification. The Self-Transition Notification must
include the EBS licensee's full name, postal mailing address, contact
person, e-mail address, and phone and fax numbers. A self-transitioning EBS
licensee must provide the following information to all BRS and EBS licensees
located in the BTA where the self-transitioning licensees GSA geographic
center point is located:
(1) The location (by street address and by geographic coordinates) of every
constructed EBS receive site that, as of the date the Self-Transition
Notification is sent, is entitled to a replacement downconverter (see
Sec. 27.1233(a)). The response must:
(i) Specify whether the downconverting antenna is mounted on a structure
attached to the building or on a free-standing structure;
(ii) Specify the approximate height above ground level of the downconverting
antenna; and
(iii) Specify, if known, the adjacent channel D/U ratio that can be
tolerated by any receiver(s) at the receive site.
(2) The location (street address and geographic coordinates) of the main
station or booster serving each EBS receive site entitled to protection,
including:
(i) The make and model of the antenna for that main station or booster,
along with the radiation pattern if it is not included within the
Commission's database;
(ii) The ground elevation, above mean sea level (AMSL), of the building or
antenna supporting structure on which the main station or booster
transmission antenna is installed;
(iii) The height above ground level (AGL) of the center of radiation of the
transmission antenna;
(iv) The orientation of the main lobe of the transmission antenna;
(v) Any mechanical beamtilt or electrical beamtilt not reflected in the
radiation pattern provided or included within the Commission's database;
(vi) The bandwidth of each channel or subchannel, the emission type for each
channel or subchannel, and the EIRP measured in the main lobe for each
channel or subchannel; and
(vii) The make and model of the receive antenna installed at that site,
along with the radiation pattern if it is not included within the
Commission's database.
(3) The number and identification of EBS video programming or data
transmission tracks the EBS licensee is entitled to receive in the MBS (see
Sec. 27.1233(b)).
[ 71 FR 35193 , June 19, 2006]
Effective Date Note: At 71 FR 35193 , June 19, 2006, Sec. 27.1236 was added.
This section contains information collection and recordkeeping requirements
and will not become effective until approval has been given by the Office of
Management and Budget.
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.