FCC 78.33 Revised as of October 1, 2006
Goto Year:2005 |
2007
Sec. 78.33 Special temporary authority.
(a) Notwithstanding the requirements of Sec. Sec. 78.15 and 78.20, in circumstances
requiring immediate or temporary use of facilities, a request may be made
for special temporary authority to install and operate new equipment or to
operate licensed equipment in a manner different from that authorized in a
station license. Any such request may be in letter form, and shall be
submitted in duplicate: Provided, however, That in cases of emergency
involving danger to life or property or due to damage to equipment, such
request may be made by telephone or telegraph with the understanding that a
written request shall be submitted within ten (10) days thereafter.
(b) Special temporary authority may also be requested to conduct a field
survey to determine necessary data in connection with the preparation of a
formal application for installation of a radio system under this part. Such
authority may be granted to equipment suppliers and others who are not
operators of cable television systems or other eligible systems, as well as
to cable operators or other eligible system operators, to conduct equipment,
program, service, and path tests.
(c) Any request for special temporary authority shall be clear and complete
within itself as to the authority requested. In addition, such requests
shall contain the following information:
(1) Name, address, and citizenship of applicant;
(2) Grounds for special action, including a description of any emergency or
damage to equipment;
(3) Type of operation to be conducted;
(4) Purpose of operation;
(5) Time and date of proposed operation;
(6) Class of station and nature of service;
(7) Location of station;
(8) Equipment to be used, specifying manufacturer, model number, and number
of units;
(9) Frequency or frequencies desired, consistent with Sec. 78.18: Provided,
however, That in the case of events of widespread interest and importance
that cannot be transmitted successfully on these frequencies, frequencies
assigned to other services may be requested on a showing that operation
thereon will not cause interference to established stations: And provided,
further, That in no case will a cable television relay service operation be
authorized on frequencies employed for the safety of life and property;
(10) Plate power input to final radio frequency stage;
(11) Type of emission;
(12) Description of antenna to be used, including height. In the event that
the proposed antenna installations will increase the height of any natural
formation, or existing manmade structure, by more than 6.1 meters (20 feet),
a vertical plan sketch showing the height of the structures proposed to be
erected, the height above ground of any existing structure, the elevation of
the site above mean sea level, and the geographic coordinates of the
proposed sites shall be submitted with the application.
(d) Except in emergencies involving safety of life or property or due to
damage to equipment, a request for special temporary authority shall be
filed at least ten (10) days prior to the date of proposed operation, or
shall be accompanied by a statement of reasons for the delay in submitting
such request.
(e) If the Commission finds that special temporary authority is in the
public interest, it may grant such authority for a period not exceeding
ninety (90) days, and, on a like finding, may extend such authority for one
additional period not to exceed ninety (90) days.
[ 37 FR 15927 , Aug. 8, 1972, as amended at 55 FR 46015 , Oct. 31, 1990; 58 FR 44952 , Aug. 25, 1993]
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.