§ 74.788 Digital construction period.
(a) Each original construction permit for the construction of a new
digital low power television or television translator station shall
specify a period of three years from the date of issuance of the
original construction permit within which construction shall be
completed and application for license filed.
(b) Any construction permit for which construction has not been
completed and for which an application for license or extension of time
has not been filed, shall be automatically forfeited upon expiration
without any further affirmative cancellation by the Commission.
(c) Authority delegated. (1) Authority is delegated to the Chief, Media
Bureau to grant an extension of time of up to six months beyond the
relevant construction period for each original construction permit upon
demonstration by the digital licensee or permittee that failure to meet
the construction deadline is due to circumstances that are either
unforeseeable or beyond the licensee's control where the licensee has
take all reasonable steps to resolve the problem expeditiously.
(2) Such circumstances shall include, but shall not be limited to:
(i) Inability to construct and place in operation a facility necessary
for transmitting digital television, such as a tower, because of delays
in obtaining zoning or FAA approvals, or similar constraints;
(ii) The lack of equipment necessary to obtain a digital television
signal; or
(iii) Where the cost of construction exceeds the station's financial
resources.
(3) The Bureau may grant no more than two extension requests upon
delegated authority. Subsequent extension requests shall be referred to
the Commission. The Bureau may deny extension requests upon delegated
authority.
(4) Applications for extension of time shall be filed no earlier than
90 and no later than 60 days prior to the relevant construction
deadline, absent a showing of sufficient reasons for filing within less
than 60 days of the relevant construction deadline.
[ 69 FR 69334 , Nov. 29, 2004]
Goto Section: 74.787 | 74.789
Goto Year: 2009 |
2011
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public