Goto Section: 25.132 | 25.134 | Table of Contents
FCC 25.133
Revised as of October 1, 2013
Goto Year:2012 |
2014
§ 25.133 Period of construction; certification of commencement of
operation.
(a)(1) Each license for an earth station governed by this part, except
for mobile earth stations, shall specify as a condition therein the
period in which construction of facilities must be completed and
station operation commenced. Construction of the earth station must be
completed and the station must be brought into operation within 12
months from the date of the license grant except as may be determined
by the Commission for any particular application.
(2) Each license for mobile earth stations shall specify as a condition
therein the period in which station operation must be commenced. The
networks in which the mobile earth stations will be operated must be
brought into operation within 12 months from the date of the license
grant except as may be determined by the Commission for any particular
application.
(b)(1) Each license for a transmitting earth station included in this
part, except for earth stations licensed under a blanket licensing
provision, shall also specify as a condition therein that upon the
completion of construction, each licensee must file with the Commission
a certification containing the following information:
(i) The name of the licensee;
(ii) File number of the application;
(iii) Call sign of the antenna;
(iv) Date of the license;
(v) A certification that the facility as authorized has been completed
and that each antenna facility has been tested and is within 2 dB of
the pattern specified in § 25.209, § 25.135 (NVNG MSS earth
stations), or § 25.213 (1.6/2.4 GHz Mobile-Satellite Service earth
stations);
(vi) The date on which the earth station became operational; and
(vii) A statement that the station will remain operational during the
license period unless the license is submitted for cancellation.
(2) For earth stations authorized under any blanket licensing provision
in this chapter, a certification containing the information in
paragraph (b)(1) of this section must be filed when the network is put
into operation.
(c) If the facility does not meet the technical parameters set forth in
§ 25.209, a request for a waiver must be submitted and approved by the
Commission before operations may commence.
(d) Each receiving earth station licensed or registered pursuant to
§ 25.131 must be constructed and placed into service within 6 months
after coordination has been completed. Each licensee or registrant must
file with the Commission a certification that the facility is completed
and operating as provided in paragraph (b) of this section, with the
exception of certification of antenna patterns.
[ 56 FR 24016 , May 28, 1991, as amended at 58 FR 68059 , Dec. 23, 1993;
59 FR 53327 , Oct. 21, 1994; 65 FR 59142 , Oct. 4, 2000; 70 FR 32254 ,
June 2, 2005; 78 FR 8421 , Feb. 6, 2013]
return arrow Back to Top
Goto Section: 25.132 | 25.134
Goto Year: 2012 |
2014
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public