  § 22.946   Construction period for Unserved Area authorizations.

   The construction period applicable to new or modified Cellular
   facilities for which an authorization is granted pursuant to the
   Unserved Area process is one year, beginning on the date the
   authorization is granted. To satisfy this requirement, a Cellular
   system must be providing service to mobile stations operated by
   subscribers and roamers. The licensee must notify the FCC (FCC Form
   601) after the requirements of this section are met. See § 1.946 of this
   chapter. See also § 22.949.

   [ 79 FR 72151 , Dec. 5, 2014]

   return arrow Back to Top


Goto Section: 22.925 | 22.947

Goto Year: 2017 | 2019
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public