  § 25.133   Period of construction; certification of commencement of operation.

   (a)(1) Each initial license for an earth station governed by this part,
   except for blanket licenses, will specify as a condition therein the
   period in which construction of facilities must be completed and
   station operation commenced. Construction of the earth station must be
   completed and the station must be brought into operation within 12
   months from the date of the license grant except as may be determined
   by the Commission for any particular application.

   (2) Operation of a network of earth stations at unspecified locations
   under an initial blanket license must commence within 12 months from
   the date of the license grant unless the Commission orders otherwise.

   (b)(1) Each initial license for a transmitting earth station or
   modified license authorizing operation of an additional transmitting
   antenna, except for blanket licenses, will also specify as a condition
   therein that upon completion of construction, the licensee must file
   with the Commission a certification containing the following
   information:

   (i) The name of the licensee;

   (ii) File number of the application;

   (iii) Call sign of the antenna;

   (iv) Date of the license;

   (v) A certification that the facility as authorized has been completed
   and that each antenna has been tested and found to perform within
   authorized gain patterns or off-axis EIRP density levels; and

   (vi) The date when the earth station became operational.

   (vii) A statement that the station will remain operational during the
   license period unless the license is submitted for cancellation.

   (2) For FSS earth stations authorized under a blanket license, the
   licensee must notify the Commission when the earth station network
   commences operation. The notification should include the information
   described in paragraphs (b)(1)(i) through (iv) of this section and a
   certification that each hub antenna, and a type of antenna used in
   remote stations in the network, has been tested and found to perform
   within authorized gain patterns or off-axis EIRP density levels. For
   any type of antenna whose performance was not certified when the
   network commenced operation, the licensee must submit the information
   and certification stated above for the antenna type when it is first
   deployed.

   (c) [Reserved]

   (d) Each receiving earth station licensed or registered pursuant to
   § 25.131 must be constructed and placed into service within 6 months
   after coordination has been completed. Each licensee or registrant must
   file with the Commission a certification that the facility is completed
   and operating as provided in paragraph (b) of this section, with the
   exception of certification of antenna patterns.

   [ 56 FR 24016 , May 28, 1991, as amended at  58 FR 68059 , Dec. 23, 1993;
    59 FR 53327 , Oct. 21, 1994;  65 FR 59142 , Oct. 4, 2000;  70 FR 32254 ,
   June 2, 2005;  78 FR 8421 , Feb. 6, 2013;  79 FR 8318 , Feb. 12, 2014;  81 FR 55330 , Aug. 18, 2016]

   return arrow Back to Top


Goto Section: 25.132 | 25.134

Goto Year: 2018 | 2020
CiteFind - See documents on FCC website that cite this rule

Want to support this service?
Thanks!

Report errors in this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public