Goto Section: 27.1235 | 27.1237 | Table of Contents
FCC 27.1236
Revised as of October 1, 2019
Goto Year:2018 |
2020
§ 27.1236 Self-transitions.
(a) If an Initiation Plan is not filed on or before January 21, 2009
for a BTA, BRS and EBS licensees in that BTA may self-transition by
relocating to their default channel locations specified in § 27.5(i)(2)
and complying with § § 27.50(h), 27.53, 27.55 and 27.1221.
(b) To self-transition, a BRS or EBS licensee must:
(1) Notify the Secretary of the Commission on or before April 21, 2009
that it will self-transition (see paragraph (a) of this section);
(2) Send a Self-Transition Notification (see paragraph (c) of this
section) to other BRS and EBS licensees in the BTA where the
self-transitioning licensee's GSA geographic center point is located
that it is self-transitioning;
(3) Notify other licensees whose GSAs overlap with the
self-transitioning licensee that it is self-transitioning.
(4) Address interference concerns with other BRS and EBS licensees in
the BTA that are also self-transitioning;
(5) File a modification application with the Commission, and
(6) Complete the self-transition on or before October 20, 2010.
(c) Self-Transition Notification. The Self-Transition Notification must
include the EBS licensee's full name, postal mailing address, contact
person, e-mail address, and phone and fax numbers. A self-transitioning
EBS licensee must provide the following information to all BRS and EBS
licensees located in the BTA where the self-transitioning licensees GSA
geographic center point is located:
(1) The location (by street address and by geographic coordinates) of
every constructed EBS receive site that, as of the date the
Self-Transition Notification is sent, is entitled to a replacement
downconverter (see § 27.1233(a)). The response must:
(i) Specify whether the downconverting antenna is mounted on a
structure attached to the building or on a free-standing structure;
(ii) Specify the approximate height above ground level of the
downconverting antenna; and
(iii) Specify, if known, the adjacent channel D/U ratio that can be
tolerated by any receiver(s) at the receive site.
(2) The location (street address and geographic coordinates) of the
main station or booster serving each EBS receive site entitled to
protection, including:
(i) The make and model of the antenna for that main station or booster,
along with the radiation pattern if it is not included within the
Commission's database;
(ii) The ground elevation, above mean sea level (AMSL), of the building
or antenna supporting structure on which the main station or booster
transmission antenna is installed;
(iii) The height above ground level (AGL) of the center of radiation of
the transmission antenna;
(iv) The orientation of the main lobe of the transmission antenna;
(v) Any mechanical beamtilt or electrical beamtilt not reflected in the
radiation pattern provided or included within the Commission's
database;
(vi) The bandwidth of each channel or subchannel, the emission type for
each channel or subchannel, and the EIRP measured in the main lobe for
each channel or subchannel; and
(vii) The make and model of the receive antenna installed at that site,
along with the radiation pattern if it is not included within the
Commission's database.
(3) The number and identification of EBS video programming or data
transmission tracks the EBS licensee is entitled to receive in the MBS
(see § 27.1233(b)).
[ 71 FR 35193 , June 19, 2006, as amended at 73 FR 26042 , May 8, 2008]
return arrow Back to Top
Goto Section: 27.1235 | 27.1237
Goto Year: 2018 |
2020
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public