§ 73.3598 Period of construction.
(a) Except as provided in the last two sentences of this paragraph (a),
each original construction permit for the construction of a new TV, AM,
FM or International Broadcast; low power TV; low power FM; TV
translator; TV booster; FM translator; or FM booster station, or to
make changes in such existing stations, shall specify a period of three
years from the date of issuance of the original construction permit
within which construction shall be completed and application for
license filed. An eligible entity that acquires an issued and
outstanding construction permit for a station in any of the services
listed in this paragraph (a) shall have the time remaining on the
construction permit or eighteen months from the consummation of the
assignment or transfer of control, whichever is longer, within which to
complete construction and file an application for license. For purposes
of the preceding sentence, an “eligible entity” shall include any
entity that qualifies as a small business under the Small Business
Administration's size standards for its industry grouping, as set forth
in 13 CFR parts 121 through 201, at the time the transaction is
approved by the FCC, and holds:
(1) 30 percent or more of the stock or partnership interests and more
than 50 percent of the voting power of the corporation or partnership
that will hold the construction permit; or
(2) 15 percent or more of the stock or partnership interests and more
than 50 percent of the voting power of the corporation or partnership
that will hold the construction permit, provided that no other person
or entity owns or controls more than 25 percent of the outstanding
stock or partnership interests; or
(3) More than 50 percent of the voting power of the corporation that
will hold the construction permit if such corporation is a publicly
traded company.
(b) The period of construction for an original construction permit
shall toll when construction is prevented by the following causes not
under the control of the permittee:
(1) Construction is prevented due to an act of God, defined in terms of
natural disasters (e.g., floods, tornados, hurricanes, or earthquakes);
(2) The grant of the permit is the subject of administrative or
judicial review (i.e., petitions for reconsideration and applications
for review of the grant of a construction permit pending before the
Commission and any judicial appeal of any Commission action thereon),
or construction is delayed by any cause of action pending before any
court of competent jurisdiction relating to any necessary local, state
or federal requirement for the construction or operation of the
station, including any zoning or environmental requirement;
(3) A request for international coordination, with respect to an
original construction permit for a new DTV station, has been sent to
Canada or Mexico on behalf of the station and no response from the
country affected has been received, or the licensee or permittee is
challenging the response from Canada or Mexico on the grounds that the
facility as approved would not permit the station to serve the
population that is both approved by the Commission and served by the
station's TV (analog) facility to be vacated by June 12, 2009;
(4) A request for international coordination, with respect to a
construction permit for stations in the Low Power FM service, on FM
channels reserved for noncommercial educational use, and for
noncommercial educational full power television stations, has been sent
to Canada or Mexico on behalf of the station and no response from the
country affected has been received; or
(5) Failure of a Commission-imposed condition precedent prior to
commencement of operation.
(c) A permittee must notify the Commission as promptly as possible and,
in any event, within 30 days, of any pertinent event covered by
paragraph (b) of this section, and provide supporting documentation.
All notifications must be filed in triplicate with the Secretary and
must be placed in the station's local public file. For authorizations
to construct stations in the Low Power FM service, on FM channels
reserved for noncommercial educational use, and for noncommercial
educational full power television stations, the Commission will
identify and grant an initial period of tolling when the grant of a
construction permit is encumbered by administrative or judicial review
under the Commission's direct purview (e.g., petitions for
reconsideration and applications for review of the grant of a
construction permit pending before the Commission and any judicial
appeal of any Commission action thereon), a request for international
coordination under paragraph (b)(4) of this section, or failure of a
condition under paragraph (b)(5) of this section. When a permit is
encumbered by administrative or judicial review outside of the
Commission's direct purview (e.g., local, state, or non-FCC Federal
requirements), the permittee is required to notify the Commission of
such tolling events.
(d) A permittee must notify the Commission promptly when a relevant
administrative or judicial review is resolved. Tolling resulting from
an act of God will automatically cease six months from the date of the
notification described in paragraph (c) of this section, unless the
permittee submits additional notifications at six-month intervals
detailing how the act of God continues to cause delays in construction,
any construction progress, and the steps it has taken and proposes to
take to resolve any remaining impediments. For authorizations to
construct stations in the Low Power FM service, on FM channels reserved
for noncommercial educational use, and for noncommercial educational
full power television stations, the Commission will cease the tolling
treatment and notify the permittee upon resolution of either:
(1) Any encumbrance by administrative or judicial review of the grant
of the construction permit under the Commission's direct purview;
(2) The request for international coordination under paragraph (b)(4)
of this section; or
(3) The condition on the commencement of operations under paragraph
(b)(5) of this section.
(e) Any construction permit for which construction has not been
completed and for which an application for license has not been filed,
shall be automatically forfeited upon expiration without any further
affirmative cancellation by the Commission.
[ 63 FR 70050 , Dec. 18, 1998, as amended at 65 FR 7648 , Feb. 15, 2000;
68 FR 12761 , Mar. 17, 2003; 69 FR 53352 , Sept. 1, 2004; 73 FR 5684 ,
Jan. 30, 2008; 73 FR 28369 , May 16, 2008; 74 FR 8879 , Feb. 27, 2009; 85 FR 7890 , Feb. 12, 2020]
Goto Section: 73.3597 | 73.3601
Goto Year: 2020 |
2022
CiteFind - See documents on FCC website that
cite this rule
Want to support this service?
Thanks!
Report errors in
this rule. Since these rules are converted to HTML by machine, it's possible errors have been made. Please
help us improve these rules by clicking the Report FCC Rule Errors link to report an error.
hallikainen.com
Helping make public information public